This example shows you how to setup an Action or Unit Based Post-Press Activity such as a Fedex Letter charge.

1. General Tab

-- 1. Enter "Your Activity Name" into Activity Name

-- 2. The Job Description will be copied automatically. Adjust if necessary.

-- 3. Select Category.

General Tab

2. Adjust the Variable Charges Settings

Note: The Calculated Rate Charge does NOT apply to Fedex Packages. However, it could very well but used to derive the "unit charge" for other activities.

3. Enter your From...To Ranges and Prices for AA, BB, CC prices